#### Risk Management
|
||||
The goal is to trade small amounts of increased overhead for large amounts of risk reduction.
|
||||
In order to commit to risk management:
|
||||
- Describe a risk management approach in writing
|
||||
- Budget funds for risk resolution and risk removal
|
||||
- Use risk assessments to update project plans, else all is for nothing
|
||||
|
||||
Tools for risk management:
|
||||
- Planning for risk management
|
||||
- Assign a risk officer
|
||||
- play devil's advocate during planning meetings and planning reviews
|
||||
- needs to have a bit of the attitude: "It will never work"
|
||||
- senior developer or senior tester
|
||||
- top 10 risk list
|
||||
-
|
||||
- risk-management plan for each risk
|
||||
- create anonymous risk-reporting channel
|
||||
- Bad news are not shared easily --> make it anonymous to facilitate. It is crucial that all team members do communicate this
|
||||
|
||||
> [!Idea] Use Jira / Github Issues for risk Tracking
|
||||
> This makes risks visible. People can discuss risks. You can assign responsibility for risk mitigation
|
||||
|
||||
##### Risk Management Plans
|
||||
Answer the following questions for every risk:
|
||||
- **Why?** Why is a risk-management plan needed for this specific risk? Describe the risk's probability of occurrence, consequences, and severity.
|
||||
- **How?** How will the risk be resolved in general? Describe the general approach to re- solving the risk. List or describe the options that were considered.
|
||||
- **What?** What specific steps will be taken to resolve the risk? List the specific steps and deliverables that will be generated in addressing the risk. Include a description of the conditions under which the risk will be upgraded— for example, if the risk cannot be resolved by a specific date.
|
||||
- **Who?** Who will be responsible for completing each step? List the specific person re- sponsible for completing each step.
|
||||
- **When?** When will each step be completed? List the completion date for each step.
|
||||
- **How much?** How much budget is allocated to the resolution of the risk? List the cost of each step that will be taken to resolve the risk.
|
||||
|
||||
#### Personnel Strategies
|
||||
- evaluate managers based on how well they retain project personnell
|
||||
- professional growth opportunities during the project
|
||||
- after the project team members should feel better about the company, not worse
|
||||
|
||||
|
||||
> [!Quote] Available vs Good
|
||||
> It's better to wait for a productive programmer to become available than it is to wait for the first available programmer to become productive.
|
||||
|
||||
Team dynamics and team bond play a more important role than individual developers' capabilities (slightly behind). This means we need to hire someone who fits into the team.
|
||||
|
||||
##### Key Staff-Buildup Questions
|
||||
- Does the project manager have software experience with one or more projects of a similar size?
|
||||
- Does project's senior technical staff have knowledge of the kind of software being built and experience on similar successful projects?
|
||||
- Most teams are comprised of average personnel. Do expectations about the team's productivity match the team members' abilities?
|
||||
- Will the individuals work well together?
|
||||
|
||||
##### Project Team Organization
|
||||
- Project manager: orchestrate detailed technical work (development, quality assurance, user documentation). Develops software development plan. Is the team's link to upper management.
|
||||
- Product manager: Business level work: marketing, product packaging, end-user documentation, end-user support. In-house projects: work with groups that use the system to define the software, setup trraining and user support
|
||||
- Architect: Responsible for conceptual integrity at design and implementation level
|
||||
- User-interface designer: responsible for conceptual integrity of software visible to end-user.
|
||||
- End-user liaison: interact with end-user throughout the project. Walk them through the prototype, demonstrate new releases, gather user feedback.
|
||||
- Developer: detailed design and implementation of software. Responsible for making the software work
|
||||
- QA/Testers: responsible for Quality Assurance and test activities. Create detailed test plans and perform tests. Find all the ways to break the software.
|
||||
- Tool smith: Responsible for developing build scripts, maintain versioning system, developing utilities needed by the project.
|
||||
- Build coordinator: responsible for maintaining and running the daily build and notifying the developers when something breaks the build
|
||||
- Risk officer: watch for emerging risks and diversion from the development plan
|
||||
- End-user documentation specialists: generate help files, documentation and instructional materials that end-users will use.
|
||||
|
||||
|
||||
|
||||
---
|
||||
## Steps towards the Software release
|
||||
1. Define requirements
|
||||
2. Create initial project estimate (budget, schedule, staffing, desired feature set).
|
||||
3.
|
||||
1. Define preliminary risks list
|
||||
2. Define requirements
|
||||
3. Create initial project estimate (budget, schedule, staffing, desired feature set).
|
||||
|
||||
|
||||
## Document List
|
||||
- Top 10 Risk List (keeps being updated) including a risk-management plan for each risk
|
||||
- Software Development Plan
|
||||
- Risk management approach
|
||||
- Risk officer
|
||||
|
||||
## Tool list
|
||||
- Anonymous risk-reporting channel
|
||||
|
||||
## Review List
|
||||
- Review Top 10 Risks every 2 Weeks (see page 97)
|
||||
---
|
||||